Pine Street: Project is nearing completion with only punchlist work remaining.

Rollwind Road: Project is nearing completion with only punchlist work remaining.

Forest Avenue: Project is nearing completion with only punchlist work remaining.

Thursday, November 3, 2011

Pine Street: Peter Baker is scheduled to complete asphalt paving on Pine Street on Friday, November 4th. Next week Berger Excavating is scheduled to continue work on punchlist items.

Rollwind Road: Peter Baker is scheduled to complete asphalt paving on Rollwind Road on Friday, November 4th . Next week Berger Excavating is scheduled to continue parkway restoration and punchlist work.

Forest Avenue: Peter Baker is scheduled to begin trench paving on Friday and Saturday, November 4th and 5th. Additionally, next week the landscaping contractor is scheduled to begin landscape restoration and punchlist work.

Friday, October 28, 2011

Pine Street: Next week the contractor is scheduled to install the final lift of asphalt, the surface course (weather permitting).

Rollwind Road: Next week the contractor is scheduled to install the final lift of asphalt, the surface course (weather permitting). Lawn restoration will take place following the completion of the asphalt.

Forest Avenue: Next week Berger Excavating is scheduled to begin trench paving. Additionally, next week the landscaping contractor is scheduled to begin landscape restoration.

Wednesday, October 19, 2011

Pine Street: This week, the contractor is scheduled to continue with parkway restoration and placement of sod. After parkway restoration is complete, the final lift of asphalt, the surface course will be paved (scheduled weather permitting for next week).

Rollwind Road: This week and in to next week, the contractor will begin parkway restoration. After parkway restoration is complete, the final lift of asphalt, the surface course will be paved (scheduled weather permitting for mid- to late- next week).

Forest Avenue: Next week Berger Excavating is scheduled to begin trench paving. Additionally, next week the landscaping contractor is scheduled to begin landscape restoration.

Friday, October 14, 2011

Pine Street: Next week, the contractor is scheduled to continue with parkway restoration. After parkway restoration is complete, the final lift of asphalt, the surface course will be paved.

Rollwind Road: Berger Excavating has completed grinding, road base prep and concrete driveways. Next week, Berger Excavating is scheduled to begin installation of the first lift of asphalt paving. Asphalt driveways are also scheduled to be restored following the roadway paving. After driveway restoration and roadway paving is complete the landscaping contractor will begin parkway restoration.

As a reminder, it is the Village of Glenview’s policy to only replace asphalt or concrete driveways. The residents are responsible for the replacement of any other types of driveways, including brick, stamped or exposed aggregate concrete, colored gravel and others. Our contractors do not have the expertise or materials to repair all of the different kinds of other driveway. If you don’t mind not having the bricks replaced we could place asphalt in the area where the bricks were removed. If you wish to have the asphalt placed instead of the bricks please notify Robert Steele, Capital Projects Department, as soon as possible by phone at (847) 486-5636, or email, rsteele@glenview.il.us.
Thank you for your patience during this project. Feel free to contact the Capital Projects Department at (847) 486-5636 if you have any questions or concerns.

Forest Avenue: Next week Berger Excavating is scheduled to begin trench paving. Additionally, next week the landscaping contractor is scheduled to begin landscape restoration.

Friday, October 7, 2011

Pine Street: Next week, the contractor is scheduled to continue with parkway restoration. After parkway restoration is complete, the final lift of asphalt, the surface course will be paved.

Rollwind Road: Berger Excavating has completed the utility work on Rollwind Road. Next week, Berger Excavating is scheduled to begin road reconstruction work. Berger Excavating will also be removing driveway aprons as necessary to complete the road reconstruction work. Berger Excavating will be placing temporary aggregate ramps to provide access to driveways during the road reconstruction. Asphalt and concrete driveways will be restored following the road reconstruction. As a reminder, it is the Village of Glenview’s policy Glenview to only replace asphalt or concrete driveways. The residents are responsible for the replacement any other types of driveways, including brick, stamped or exposed aggregate concrete, colored gravel and others. Our contractors do not have the expertise or materials to repair all of the different kinds of other driveway. If you don’t mind not having the bricks replaced we could place asphalt in the area where the bricks were removed. If you wish to have the asphalt placed instead of the bricks please notify Robert Steele, Capital Projects Department, as soon as possible by phone at (847) 486-5636, or email, rsteele@glenview.il.us. Thank you for your patience during this project. Feel free to contact the Capital Projects Department at (847) 486-5636 if you have any questions or concerns.

Forest Avenue: This week and next week, Berger Excavating will continue work on storm sewer installation.

Friday, September 30, 2011

Pine Street: The first layer of asphalt has been placed on the road and driveways are now accessible. During the week of October 3rd, the contractor will begin landscaping restoration, completing asphalt driveways, and other miscellaneous items. The final layer of asphalt will complete the project in a couple of weeks.
Thank you for your patience during this project. Feel free to contact Robert Steele, Capital Projects Department at (847) 486-5636 if you have any questions or concerns.