Friday, October 14, 2011

Pine Street: Next week, the contractor is scheduled to continue with parkway restoration. After parkway restoration is complete, the final lift of asphalt, the surface course will be paved.

Rollwind Road: Berger Excavating has completed grinding, road base prep and concrete driveways. Next week, Berger Excavating is scheduled to begin installation of the first lift of asphalt paving. Asphalt driveways are also scheduled to be restored following the roadway paving. After driveway restoration and roadway paving is complete the landscaping contractor will begin parkway restoration.

As a reminder, it is the Village of Glenview’s policy to only replace asphalt or concrete driveways. The residents are responsible for the replacement of any other types of driveways, including brick, stamped or exposed aggregate concrete, colored gravel and others. Our contractors do not have the expertise or materials to repair all of the different kinds of other driveway. If you don’t mind not having the bricks replaced we could place asphalt in the area where the bricks were removed. If you wish to have the asphalt placed instead of the bricks please notify Robert Steele, Capital Projects Department, as soon as possible by phone at (847) 486-5636, or email, rsteele@glenview.il.us.
Thank you for your patience during this project. Feel free to contact the Capital Projects Department at (847) 486-5636 if you have any questions or concerns.

Forest Avenue: Next week Berger Excavating is scheduled to begin trench paving. Additionally, next week the landscaping contractor is scheduled to begin landscape restoration.