Thursday, November 3, 2011

Pine Street: Peter Baker is scheduled to complete asphalt paving on Pine Street on Friday, November 4th. Next week Berger Excavating is scheduled to continue work on punchlist items.

Rollwind Road: Peter Baker is scheduled to complete asphalt paving on Rollwind Road on Friday, November 4th . Next week Berger Excavating is scheduled to continue parkway restoration and punchlist work.

Forest Avenue: Peter Baker is scheduled to begin trench paving on Friday and Saturday, November 4th and 5th. Additionally, next week the landscaping contractor is scheduled to begin landscape restoration and punchlist work.